Rodriguez Transfer manufactures conveyor belts. Early in July 2016, Rodriguez Transfer constructed its own building at a

Question:

Rodriguez Transfer manufactures conveyor belts. Early in July 2016, Rodriguez Transfer constructed its own building at a materials, labor, and overhead cost of $980,000. Rodriguez Transfer paid cash for the construction costs. Rodriguez Transfer also paid for architect fees and building permits of $70,000.

Requirements

1. How much should Rodriguez Transfer record as the cost of the building in 2016?

2. Record Rodriguez Transfer's transactions related to the construction of the building?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Financial Accounting

ISBN: 978-0134436111

4th edition

Authors: Robert Kemp, Jeffrey Waybright