A major criterion for selecting the winning bid besides low cost is the time required to produce the part. However, if the company is awarded the contract it will be held strictly to the completion date specified in the bid, and any delays will result in severe financial penalties. In order to determine the project completion time to put in its bid, the company has identified the project activities, precedence relationships, and activity times shown in the following table:
If RusTech, Inc., wants to be 90% certain that it can deliver the part without incurring a penalty, what time frame should it specify in thebid?