Question: A sewer pipe is to be laid from station 10+00 to station 13+20 on a -1% grade, starting with invert elevation 326.32ft. At 10+00 Calculate

A sewer pipe is to be laid from station 10+00 to station 13+20 on a -1% grade, starting with invert elevation 326.32ft. At 10+00 Calculate invert elevations at each 50ft station along line.