Question: Sid Davidson was able to determine the activity times for the leadership training program. He would like to determine the total project completion time and
ACTIVITY TIME (DAYS)
A ............ 2
B ............ 5
C ............ 1
D ............ 10
E ............ 3
F ............ 6
G ............ 8
35
Step by Step Solution
3.34 Rating (175 Votes )
There are 3 Steps involved in it
Critical Activity ES EF LS LF Stack Activity A 0 2 13 15 13 No B 0 5 ... View full answer