Question: Six Jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows:
Six Jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows:
.png)
Determine a sequence that will minimize the total completion time for these jobs. Illustrategraphically.
Job Operation 1 (hours) Oation 2 (Chours) 10
Step by Step Solution
3.35 Rating (179 Votes )
There are 3 Steps involved in it
Job Operation 1 Hours Operation 2 Hours A 10 5 B 7 ... View full answer