Question: Some tasks and the order in which they must be performed according to their assembly requirements are shown in the following table. These are to
Some tasks and the order in which they must be performed according to their assembly requirements are shown in the following table. These are to be combined into workstations to create an assembly line. The assembly line operates 71/ 2 hours per day. The output requirement is 1,000 units per day.
.png)
a. What is the workstation cycle time required to produce 1,000 units per day?
b. Balance the line using the longest task time based on the 1,000- unit forecast, stating which tasks would be done in each workstation.
c. For (b), what is the efficiency of your line balance, assuming it is running at the cycle time from part (a)?
d. After production was started, Marketing realized that it understated demand and must increase output to 1,100 units. What action would you take? Be specific and quantitative in youranswer.
PRECEDING TIME PRECEDING TIME TASKS TASK TASKS (SECONDS) 15 24 TAsK SECONDS) 14 12 F G H, I J, K 18 15 10
Step by Step Solution
3.59 Rating (163 Votes )
There are 3 Steps involved in it
a C production time per dayrequired output per day 7... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
287-B-M-L-S-C-M (1402).docx
120 KBs Word File
