The following information relates to Bruce Limited: Actual hours: 1000. Actual wage rate per hour: 6.50. Standard

Question:

The following information relates to Bruce Limited: 

Actual hours: 1000.
Actual wage rate per hour: £6.50.
Standard hours for actual production: 900.
Standard wage rate per hour: £6.00. 


Required:

Calculate the following variances:

(a) Direct labour total

(b) Direct labour rate

(c) Direct labour efficiency.  