Question: When using the PERT method for network analysis, the critical path through the network is the a. shortest path through the network. b. longest path
When using the PERT method for network analysis, the critical path through the network is the
a. shortest path through the network.
b. longest path through the network.
c. path with the most slack.
d. path with the most variability in estimated times.
e. least-cost path,