Question: Estimate the duration of activity D using the PERT method, knowing that it has an optimistic time estimate of 3 days, a most likely estimate
- Estimate the duration of activity D using the PERT method, knowing that it has an optimistic time estimate of 3 days, a most likely estimate of 4 days, and a pessimistic estimate of 11 days.
- Draw a Network Diagram of this project (you can use drawings in Word)
- Find the critical path and the shortest time to complete project
- Calculate the ES, LS, EF, LF, and Slack time for each task in the network (you can enter such information into the boxes of tasks on the network diagram)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
