Question: When preparing a bid on a large construction project, a contractor analyzes how long each phase of the construction will take. Suppose that the contractor
When preparing a bid on a large construction project, a contractor analyzes how long each phase of the construction will take. Suppose that the contractor estimates that the time required for the electrical work will be X hundred worker-hours, where X is a random variable with density function f (x) = x(6 - x)/18, 3 ≤ x ≤ 6. (See Fig. 3.)
(a) Find the cumulative distribution function F (x).
(b) What is the likelihood that the electrical work will take less than 500 worker-hours?
(c) Find the mean time to complete the electrical work.
(d) Find Var (X ).
.5 Y f(x) = 0 x(6 - x) 18 3 Time required Figure 3 Density function for construc- tion bid. X 6
Step by Step Solution
3.31 Rating (166 Votes )
There are 3 Steps involved in it
a b c Thus the mean complet... View full answer
Get step-by-step solutions from verified subject matter experts
