Question: Develop an administrative estimate for a project involving two buildings with an estimated cost of $7 million each. Both buildings will be constructed at the
Develop an administrative estimate for a project involving two buildings with an estimated cost of $7 million each. Both buildings will be constructed at the same time but on opposite ends of a large site; 2,500 feet apart. Project durations for both buildings are 28 weeks, and they will be done concurrently but have a one-month stagger-start.
Step by Step Solution
3.64 Rating (151 Votes )
There are 3 Steps involved in it
Administrative Estimate for a TwoBuilding Project Project Parameters Number of buildings 2 Building cost per building 7 million Total project cost 14 ... View full answer