Question: A junior project manager is studying for her PMP exam, and asks you for advice. Shes learning about Earned Value Management, and wants to know
A junior project manager is studying for her PMP exam, and asks you for advice. She’s learning about Earned Value Management, and wants to know which of the variables represents the difference between what you expect to spend on the project and what you’ve actually spent so far. What should you tell her?
A. Actual Cost (AC)
B. Cost Performance Index (CPI)
C. Earned Value (EV)
D. Cost Variance (CV)