Question: A project manager decides to create a model to represent the project risks. The model translates the uncertainties specified at a detailed level into their
A project manager decides to create a model to represent the project risks. The model translates the uncertainties specified at a detailed level into their potential impact and probabilities. This technique is called a:
a. Risk model.
b. Simulation.
c. Computer risk program.
d. Decision tree.