Question: A project manager has recently communicated a to-complete performance index of 1.0 to the project sponsor. What does this mean? A. That it will be
A project manager has recently communicated a to-complete performance index of 1.0 to the project sponsor. What does this mean?
A. That it will be difficult to complete the project within set targets B. That the project must continue performing at the current rate to complete within target C. That it will be relatively easy to complete the project within set targets D. That it will be impossible to complete the project within set targets