Question: A project manager has structured his Agile project in a less prescriptive way to be less disruptive to the team. He and the team focus

A project manager has structured his Agile project in a less prescriptive way to be less disruptive to the team. He and the team focus on driving work through a continuous flow as a way of delivering value to the customer versus using iterations. This approach is associated with which Agile method?

A. Scrum B. Feature-driven development C. Crystal D. Kanban method

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!