Question: A project manager hears a rumor through the project team that the client for the project is supposed to visit the project team office and

A project manager hears a rumor through the project team that the client for the project is supposed to visit the project team office and present the project manager with a purchase order for a large change in the project. The change will authorize new budget for $50,000. This is an example of what type of communications?

a. Formal

b. Informal

c. Verbal

d. Nonwritten