Question: A project manager is developing a high-level summary timeline of the schedule, based on the product road map, in collaboration with the team. This exercise

A project manager is developing a high-level summary timeline of the schedule, based on the product road map, in collaboration with the team. This exercise will determine the number of sprints that are included within the release. Which tool or technique is the project manager and team using to develop the schedule?

A. Agile release planning B. Sprint planning C. Schedule network analysis D. Release-driven development