Question: A project manager is in the process of developing the project charter and is using a hybrid project management approach. Almost immediately, he identifies several
A project manager is in the process of developing the project charter and is using a hybrid project management approach. Almost immediately, he identifies several constraints.
Where is he likely to document the constraints and maintain regular updates as they change throughout the project?
A. Product vision B. Sprint backlog C. Risk register D. Assumption log