Question: A project manager is managing a project where a risk occurs. There is no plan to respond to this risk. The response to a negative
A project manager is managing a project where a risk occurs. There is no plan to respond to this risk. The response to a negative risk event that has no plan is called:
a. Repair order.
b. Workaround.
c. Risk mitigation.
d. Risk deflection.