Question: A project manager is negotiating with a contractor. Neither has a good idea of how long the project will take, or how much the materials
A project manager is negotiating with a contractor. Neither has a good idea of how long the project will take, or how much the materials will cost. Which contract type is MOST appropriate for this project?
A. Cost plus fixed fee (CPFF)
B. Time and Materials (T&M)
C. Cost plus award fee (CPAF)
D. Firm fixed price (FFP)