Question: A project manager is preparing to lead a project status meeting later that afternoon. The project is currently 75 percent complete and is reaching the

A project manager is preparing to lead a project status meeting later that afternoon. The project is currently 75 percent complete and is reaching the most critical point. Since the project sponsor is planning on attending the meeting, the project manager decides to update the earned value calculations to present the latest performance updates in terms that the sponsor will want to see. The budget at completion (BAC) is set at $550,000, and the current estimate at completion (EAC) is at $525,000. How is the project performing in terms of the budget?

A. It is under the planned cost.

B. It is on the planned cost.

C. It is over the planned cost.

D. Insufficient information was provided.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!