Question: A project manager is running a data center installation project. He finds that his stakeholder is angry because hes run over his budget because the
A project manager is running a data center installation project. He finds that his stakeholder is angry because he’s run over his budget because the staff turned out to be more expensive than planned. The stakeholder’s unhappy that when the project is over, the servers won’t have as much drive space as he needs. Which of the following constraints was not affected by this problem?
A. Quality B. Resource C. Time D. Cost
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts