Question: A project manager is using a hybrid approach to manage his project. He sits down with the projects sponsor to update him on progress achieved
A project manager is using a hybrid approach to manage his project. He sits down with the project’s sponsor to update him on progress achieved to date. To aid the discussion, the project manager displays a chart that visually shows how much work remains versus how much time is left for the project. What is the project manager displaying?
A. A burnup chart B. A Gantt chart C. A burndown chart D. A radar chart