Question: A project manager is using a predictive approach to managing her project. Recently, she has experienced several adjustments to the project. All of the following
A project manager is using a predictive approach to managing her project. Recently, she has experienced several adjustments to the project. All of the following result in a change request, except for which one?
A. Updates to project documents B. Corrective actions C. Preventive actions D. Defect repairs