Question: A project manager is using the earned value reporting system to manage his project. At this point in time the EV is $24,000, the BAC
A project manager is using the earned value reporting system to manage his project. At this point in time the EV is $24,000, the BAC is
$97,000, the PV is $29,000, and the AC is $45,000. What is the percent complete?
a. 30%
b. 25%
c. 46%
d. 53%