Question: A project manager working on a large project finds that there are several risks that have a severity that is higher than the acceptable risk
A project manager working on a large project finds that there are several risks that have a severity that is higher than the acceptable risk tolerance.
They cannot be avoided or deflected. The project manager will need to use which of the following approaches?
a. Change the risk tolerance of the client
b. Buy insurance for the risk
c. Ignore the risk
d. Mitigate the risk