Question: As a proactive approach to dealing with a recent issue, the project team has been asked to determine all the possible causes of the issue.

As a proactive approach to dealing with a recent issue, the project team has been asked to determine all the possible causes of the issue. Which of the following tools would be the best choice for the project team to use?

A. Histogram B. Scatter diagram C. Cause-and-effect diagram D. Control chart