Question: As you are executing your project you are constantly checking your risk register to be sure that you have planned responses for all of your
As you are executing your project you are constantly checking your risk register to be sure that you have planned responses for all of your risks. At one team status meeting, you find that a lower-priority risk has suddenly become more likely. Where do you keep information about low-priority risks?
A. Triggers B. The watchlist C. Risk Management Plan D. Qualitative analysis documents