Question: Dave is the project manager for a construction project that is building a gazebo. When the project first started, he met with the stakeholders to
Dave is the project manager for a construction project that is building a gazebo. When the project first started, he met with the stakeholders to define the scope. The sponsors mentioned that the gazebo is a really important part of their daughter’s wedding ceremony that was planned for seven months from then. In fact, they said that if the gazebo couldn’t be completed in seven months, it wouldn’t be worth it for them to even start the project. Dave wrote down the seven-month deadline to put in his Project Scope Statement. In which section of the document did the deadline appear?
A. Project Deliverables B. Project Objectives C. Project Constraints D. Project Assumptions