Question: David is a project manager working for a prominent book publishing company. As part of his latest project, he uses an approach that yields frequent

David is a project manager working for a prominent book publishing company. As part of his latest project, he uses an approach that yields frequent smaller deliverables throughout the span of the project. What type of project life cycle is David using?

A. Predictive B. Incremental C. Waterfall D. Agile