David is a project manager working for a prominent book publishing company. As the most senior project manager within the organization, he often gets the most complex project assignments. For this reason, the PMO manager assigns David to manage a project for a sponsor who is notorious for scope creep. Knowing this, David is likely to place greater emphasis on what project management process?
A. Validate Scope B. Monitor and Control Project Work C. Control Quality D. Control Scope