Question: For the following simple seven-activity project, develop a precedence network, calculate all relevant characteristics of each activity (ES, EF, LS, LF, TF), and the project
For the following simple seven-activity project, develop a precedence network, calculate all relevant characteristics of each activity (ES, EF, LS, LF, TF), and the project duration. Then go through a repetitive process to expedite the project on a least-cost basis until the project is crashed. The solution should include the precedence diagram and calculations for each activity, and then the cyclical calculation to shorten the project activity by activity in a least-cost manner. What isthe total cost of the crashed project? Why is this less than the sum of the crashed costs for the seven activities?
| Activity | Relationships | Normal Duration | Crash Duration | Normal Cost | Crash Cost |
|---|---|---|---|---|---|
| A | 3 | 2 | $$ 3,000$ | $$ 3,150$ | |
| B | A: FS | 4 | 3 | $$ 4,000$ | $$ 4,250$ |
| C | B: FS | 3 | 1 | $$ 6,500$ | $$ 7,000$ |
| D | A: FS | 4 | 2 | $$ 6,000$ | $$ 6,500$ |
| E | D: FS | 4 | 2 | $$ 3,500$ | $$ 3,900$ |
| F | A: FS | 5 | 2 | $$ 2,200$ | $$ 2,725$ |
| G | C, E, F: FS | 6 | 4 | $$ 3,900$ | $$ 5,000$ |
Step by Step Solution
There are 3 Steps involved in it
I can help you with that Precedence Network Diagram The precedence network diagram for this project is as follows Terbuka di jendela baru wwwstudocucom precedence network diagram for a sevenactivity p... View full answer
Get step-by-step solutions from verified subject matter experts
