Question: For the following simple seven-activity project, develop a precedence network, calculate all relevant characteristics of each activity (ES, EF, LS, LF, TF), and the project

For the following simple seven-activity project, develop a precedence network, calculate all relevant characteristics of each activity (ES, EF, LS, LF, TF), and the project duration. Then go through a repetitive process to expedite the project on a least-cost basis until the project is crashed. The solution should include the precedence diagram and calculations for each activity, and then the cyclical calculation to shorten the project activity by activity in a least-cost manner. What isthe total cost of the crashed project? Why is this less than the sum of the crashed costs for the seven activities?

ActivityRelationshipsNormal DurationCrash DurationNormal CostCrash Cost
A
32$$ 3,000$$$ 3,150$
BA: FS43$$ 4,000$$$ 4,250$
CB: FS31$$ 6,500$$$ 7,000$
DA: FS42$$ 6,000$$$ 6,500$
ED: FS42$$ 3,500$$$ 3,900$
FA: FS52$$ 2,200$$$ 2,725$
GC, E, F: FS64$$ 3,900$$$ 5,000$

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

I can help you with that Precedence Network Diagram The precedence network diagram for this project is as follows Terbuka di jendela baru wwwstudocucom precedence network diagram for a sevenactivity p... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!