Question: Match the term with its corresponding description. Term A. Burnup chart B. Lead time C. Velocity D. Cycle time E. Schedule performance index Description 1.
Match the term with its corresponding description.
Term A. Burnup chart B. Lead time C. Velocity D. Cycle time E. Schedule performance index Description 1. The total time it takes to deliver an item, measured from the time the work is committed to the time it is completed 2. The time required to process a work item 3. A measurement of the schedule efficiency expressed as a ratio of earned to planned value 4. A visual depiction of the work completed 5. The sum of story point sizes for the features completed in an iteration
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts