Question: Midway through the delivery of development services, a customer requested that new requirements be incorporated. When asked to submit a change request to modify the

Midway through the delivery of development services, a customer requested that new requirements be incorporated. When asked to submit a change request to modify the terms of the contract, the customer refused and insisted that the changes be implemented at no cost. After multiple discussions, neither party changed their stance on the situation. What technique will the project manager likely use to address this situation?

A. Claims administration B. Alternative dispute resolution C. Inspection D. Conflict management