Question: One multi-project organization has 37 projects active, with an average of 200 tasks for each project. Projects span 20 weeks in average duration. There are

One multi-project organization has 37 projects active, with an average of 200 tasks for each project. Projects span 20 weeks in average duration.

There are 25 resource pools and each has an average share of the project work. If you were a manager of one resource pool, how many of those tasks would you expect to look at in any given week, in order to update work being done and prepare for upcoming tasks?

Step by Step Solution

There are 3 Steps involved in it