Ron is a developer working on a release of a new smartphone application. He and his team are using Scrum to execute the work. Ron has just completed work on the user story he is tasked with for the current sprint and reviews the criteria to ensure that they are complete and ready for customer use. What are the criteria known as?

A. Acceptance criteria B. Definition of done C. Value stream mapping D. Plan-Do-Check-Act