Question: Some projects have a fi xed due date while others have to be fi nished as early as possible, and the project manager only makes
Some projects have a fi xed due date while others have to be fi nished as early as possible, and the project manager only makes commitments on the completion date once she and her project management team have scheduled the project. Explain how the backward pass differs for these two project types.