Question: The project management plan might require changes and updates as the Planning processes proceed. These updates are decided upon and managed through which of the
The project management plan might require changes and updates as the Planning processes proceed. These updates are decided upon and managed through which of the following?
A. Approved change requests B. Perform Integrated Change Control process C. Control Communications process D. Control Scope process