Question: The project manager for a design project is using the Define Scope process. Which BEST describes this? A. Creating a document that lists all of
The project manager for a design project is using the Define Scope process. Which BEST describes this?
A. Creating a document that lists all of the features of the product B. Creating a plan for managing changes to the scope baseline C. Creating a document that describes all of the work the team does to make the deliverables D. Creating a graphical representation of how the phases or deliverables decompose into work packages