Question: The project team working on a project printing 3,500 technical manuals for a hardware manufacturer cant inspect every single manual, so they take a random
The project team working on a project printing 3,500 technical manuals for a hardware manufacturer can’t inspect every single manual, so they take a random sample and verify that they have been printed correctly. This is an example of:
A. Root cause analysis B. Cost benefit analysis C. Benchmarking D. Statistical sampling