Question: The table and graph that follows represent a contractors overdraft requirements for a project. Complete the table shown for costs, markup, total worth, retainage, and

The table and graph that follows represent a contractor’s overdraft requirements for a project. Complete the table shown for costs, markup, total worth, retainage, and pay received.

Retainage is 10%, markup is 10%, and interest is 1% per month.

The client is billed at the end of the month. Payment is received the end of the next month, to be deposited in the bank the first of the following month.

Overdraft Interest Cumulative -50,000 500 -50,500 -120,500 -1,205 -121,705 -50.000 -71,000 -120,500

-82,205 -822 -83,027 82,205 10,336 -13,727 -137 -13,864 +10,336 +10,336

Overdraft Interest Cumulative -50,000 500 -50,500 -120,500 -1,205 -121,705 -50.000 -71,000 -120,500 -82,205 -822 -83,027 82,205 10,336 -13,727 -137 -13,864 +10,336 +10,336

Step by Step Solution

3.32 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Solutions Step 1 Given Direct cost 10 000 Indirect cost 5 000 Markup 10 Retainage 10 Interest 1 per ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Construction Project Management Questions!