Question: Three activities are done in sequence. Each activity takes five days to do. There is a 90% probability that each activity will be completed on

Three activities are done in sequence. Each activity takes five days to do. There is a 90% probability that each activity will be completed on time and a 10% probability that each activity will be finished late. What is the probability that the last of the three activities will be finished on time?

a. .90

b. .73

c. .27

d. .81