Question: Using a triangular distribution formula, calculate the cost estimate based on the following three-point estimates: Optimistic = $2,500, Most Likely = $3,500, Pessimistic = $7,200.

Using a triangular distribution formula, calculate the cost estimate based on the following three-point estimates: Optimistic = $2,500, Most Likely = $3,500, Pessimistic = $7,200.

A. $4,400 B. $3,950 C. $13,200 D. $3,500