Question: What can be said about this process? a. The process is not in control and should be adjusted. b. The process is in control and

What can be said about this process?9 A.M. 10 A.M. 11 A.M. 12 A.M. 1 P.M. XR X

a. The process is not in control and should be adjusted.

b. The process is in control and should not be adjusted.

c. The value of R is too high at 11 ..

d. The value for X bar is outside the control limits.

9 A.M. 10 A.M. 11 A.M. 12 A.M. 1 P.M. XR X bar 125 126 127 128 129 2 1 4 2 3