Question: When is a project considered successful? A. When the project budget is consumed, the scope is developed, and the schedule milestones are achieved B. When
When is a project considered successful?
A. When the project budget is consumed, the scope is developed, and the schedule milestones are achieved B. When the project budget is consumed and the schedule milestones are achieved C. When project benefits are realized and the stakeholder needs and expectations are met D. When objectives are achieved and the stakeholder needs and expectations are met