Question: When making changes to the planned project, dont forget to: a. Remove buffers, re-resolve resource contention, re-identify the critical chain/critical path b. Make required buffer

When making changes to the planned project, don’t forget to:

a. Remove buffers, re-resolve resource contention, re-identify the critical chain/critical path

b. Make required buffer adjustments

c. Leave buffer sizes and placements as is

d. All of the above

e. Only a and b above