Question: You are a contract project manager working for a customer who uses a predictive lifecycle approach and have entered into the activities definition phase of

You are a contract project manager working for a customer who uses a predictive lifecycle approach and have entered into the activities definition phase of your project.

You take the team through a decomposition activity to break down work packages into activities. Before concluding this phase, what else are you and the team likely to capture?

A. The activity list B. The milestone list C. The network diagram D. The list of predecessors and successors