Question: You are a project manager for a software project. As you are defining the scope of the work you need to do, you sit down
You are a project manager for a software project. As you are defining the scope of the work you need to do, you sit down with all of the project’s stakeholders and record all of the requirements you can get from them.
Which of the following is NOT a valid requirement from stakeholder analysis?
A. The work the team does must be better than they did on their last project B. There can be no more than 5% schedule variance on the project C. The quality of the product must fit within organizational metrics for software quality D. The budget must be within 10% of our projected cost
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts