Question: You are a project manager for a software project. Your team buys a component for a web page but they run into defects when they
You are a project manager for a software project. Your team buys a component for a web page but they run into defects when they use it. Those defects slow your progress down considerably. Fixing the bugs in the component will double your development schedule and building your own component will take even longer. You work with your team to evaluate the cost and impact of all of your options and recommend hiring developers at the company that built the component to help you address problems in it. That will cost more but it will reduce your delay by a month. What is your next step?
A. Fix the component B. Write up the change request and take it to the change control board C. Start Plan Procurements so you can get the contract ready for the vendor D. Change the Scope Baseline to include your recommendation