Question: You are a project manager working in an organization that is considered to be a weak matrix organizational type. You are two months into a
You are a project manager working in an organization that is considered to be a weak matrix organizational type. You are two months into a four-month project when the functional manager for half of your most critical resources announces that she will be reallocating them to another project. You explain to her that this will result in early closure of your project and that resources should not be redirected. If the functional manager succeeds in reallocating the resources, what type of ending will the project experience?
A. Extinction B. Starvation C. Integration D. Addition